HISTORY - Page 69
resumed in January 1958. Some portions of this program, such as construction of a nose cone assembly and
check-out facility, had been static since May 1957
94
.
FY 1959 funds experienced roughly the same pattern as the two preceding fiscal years. The Army planned
program reflected a figure of almost $300 million; but, in July 1958, the Air Force made a move to scale the
program down to three squadrons and remove all mobility requirements. This did not become a cold fact
until October and, thus, funds were committed that were not recoverable. The Air Force figures were
placed at $225 million, but the final amount was about $229 million
95
. Besides the impact on the over-all
program, this action represented but another example of the difficulty that ABMA fiscal planners
experienced. The scaling down of funds also continued during Fiscal Years 1960 and 1961
96
.
VI. TRAINING
JUPITER training followed the circuitous path of the development program, and considering its late start
the accomplishment was probably more difficult. This was borne out by the fact that when the program
was first approved there was no clear delineation as to which service would employ the land-based
version. Quite naturally in the first months after system authorization, the Army expended considerable
_____________________________
94. Hist, ABMA, Jul-Dec 57, p. 5; Memo, S/D to S/A, 13 Aug 57; JUP Prog Rpt for Jul 57, 8 Aug 58; JUP Prog Rpt for Jan 58, 8 Feb 58, Hist Off files. Also see Appendix 11 for Air Force
reimbursements.
95. Hist, ABMA, Jul-Dec 58, pp. 9-19; JUP Prog Rpt for Mar 59, 8 Apr 59, Hist Off files.
96. Hist, ABMA, Jul-Dec 59, p. 5.
Jupiter SM-78 Weapon System
I&C Team 2, Çigli AB, Turkey 1961-1962
Chrysler Corporation Missile Division